3.18. a. Given the following master schedule, fill in the projected available and available- to-promise rows: On

Question:

3.18.

a. Given the following master schedule, fill in the projected available and available- to-promise rows:

On hand: 10 Lot size: 75 Week 1

2 3

4 5

6 7

8 Forecast 40 40 40 40 30 30 50 50 Customer Orders 60 45 30 35 10 5

5 0

Projected Available Available to Promise MPS

b. A customer wants an order of 15 in period 2. Can it be accepted?

c. What is the possibility of accepting an order of 30 units in week 5?

d. Continued from part

b, find the possibility of accepting an order of 25 units in week 3.

e. Can we accept an order of 75 units in week 7?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Introduction To Materials Management

ISBN: 9781292162355

8th Global Edition

Authors: J. R. Tony Arnold, Chapman, Stephen N., Lloyd M. Clive

Question Posted: