Question: 4.15. Given the following product tree, explode, offset, and determine the gross and net requirements. All lead times are 1 week, and the quantities required
4.15. Given the following product tree, explode, offset, and determine the gross and net requirements. All lead times are 1 week, and the quantities required are shown in parentheses. The master production schedule calls for the completion of 100 As in week 4 and 50 in week 5. There are 300 Bs scheduled to be received in week 1 and 200 Ds in week 3. There are also 20 As available.

B(2) A C(1) sbob D(1) E(1) D(2) B(1) HD(1) E(1)
Step by Step Solution
There are 3 Steps involved in it
To solve this problem we need to break down the product structure calculate gross and net requirements and determine planned order releases for each c... View full answer