5.6. Over a period of 4 weeks, a work center produced 40, 44, 38, and 42 standard...

Question:

5.6. Over a period of 4 weeks, a work center produced 40, 44, 38, and 42 standard hours of work. What is the demonstrated capacity of the work center?