6.18 Todays date is 150. Orders A, B, and C have the following due dates and lead...
Question:
6.18 Today’s date is 150. Orders A, B, and C have the following due dates and lead time remaining. Calculate the actual time remaining and the critical ratio for each.Lead TimeActual TimeOrderDue DateRemaining (days)Remaining (days)CRA16020B16520C17520CASE