A process costs $200 to set up. The run time is 5 minutes per piece and the
Question:
A process costs $200 to set up. The run time is 5 minutes per piece and the run cost is
$30 per hour. Determine:
a. The fixed cost.
b. The variable cost.
c. The total cost and unit cost for a lot of 500.
d. The total cost and unit cost for a lot of 1000.
LO.1