A work center consisting of 3 machines operates 40 hours a week. In a 4-week period, it
Question:
A work center consisting of 3 machines operates 40 hours a week. In a 4-week period, it actually worked 360 hours and produced 468 standard hours of work. Calculate the utilization and efficiency of the work center. What is the demonstrated weekly capacity of the work center?
LO.1
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Introduction To Materials Management
ISBN: 9780132337618
6th Edition
Authors: J. R. Tony Arnold, Chapman, Stephen N., Lloyd M. Clive
Question Posted: