An order for 100 of a product is processed on work centers A and B. The setup
Question:
An order for 100 of a product is processed on work centers A and B. The setup time on A is 50 minutes, and run time is 5 minutes per piece. The setup time on B is 60 minutes, and the run time is 5 minutes per piece. Wait time between the two operations is 5 hours.
The move time between A and B is 40 minutes. Wait time after operation B is 5 hours, and the move time into stores is 3 hours. Queue at work center A is 25 hours and at B is 35 hours. Calculate the total manufacturing lead time for the order. LO.1
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Introduction To Materials Management
ISBN: 9780132337618
6th Edition
Authors: J. R. Tony Arnold, Chapman, Stephen N., Lloyd M. Clive
Question Posted: