Complete the following table. Lead time for the part is two weeks. The lot size is 100.

Question:

Complete the following table. Lead time for the part is two weeks. The lot size is 100.

What is the projected available at the end of week 3? When is it planned to release an order?

Week 1 2 3 4 Gross Requirements 20 65 35 25 Scheduled Receipts 100 Projected Available 40 Net Requirements Planned Order Receipt Planned Order Release LO.1