After constructing the project network, she now is ready for the following steps. (a) Find all the

Question:

After constructing the project network, she now is ready for the following steps.

(a) Find all the paths and path lengths through this project network. Which of these paths is a critical path?

(b) Find the earliest times, latest times, and slack for each activity. Use this information to determine which of the paths is a critical path.

(c) It is now one week later, and Christine is ahead of schedule.

She has already selected a location for the sales meeting, and all the other activities are right on schedule. Will this shorten the length of the project? Why or why not?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Introduction To Operations Research

ISBN: 9780072321692

7th Edition

Authors: Frederick S. Hillier, Gerald J. Lieberman

Question Posted: