A personnel director wishes to compare the effectiveness of two methods of training industrial employees to perform

Question:

A personnel director wishes to compare the effectiveness of two methods of training industrial employees to perform a certain assembly operation. A number of employees are to be divided into two equal groups: the first receiving training method 1 and the second training method 2. Each will perform the assembly operation, and the length of assembly time will be recorded. It is expected that the measurements for both groups will have a range of approximately 8 minutes. For the estimate of the difference in mean times to assemble to be correct to within 1 minute with a probability equal to 0.95, how many workers must be included in each training group?