MATERIALS AND LABOR VARIANCES Camisa Company produces single-colored t-shirts. Materials for the shirts are dyed in large
Question:
MATERIALS AND LABOR VARIANCES Camisa Company produces single-colored t-shirts. Materials for the shirts are dyed in large vats. After dying the materials for a given color, the vats must be cleaned and prepared for the next batch of materials to be colored. The following standards for changeover for a given batch have been established:
Direct materials (2.5 lbs. @ $0.90) $2.25 Direct labor (0.75 hr. @ $7.00) 5.25 Standard prime cost $7.50 During the year, 53,000 pounds of material were purchased and used for the changeover activity. There were 20,000 batches produced, with the following actual prime costs:
Direct materials $42,000 Direct labor 102,000 (for 14,900 hrs.)
Required:
Compute the materials and labor variances associated with the changeover activity, labeling each variance as favorable or unfavorable.
Exercise
Step by Step Answer:
Cornerstones Of Financial Accounting Current Trends Update
ISBN: 9781111527952
1st Edition
Authors: Jay Rich , Jeff Jones, Maryanne Mowen , Don Hansen