During 2019, Nilsen Company started a construction job with a contract price of $1,600,000. The job was completed in 2021. The following information is available.

image text in transcribed


Instructions

a. Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.

b. Prepare all necessary journal entries for 2020.

c. Compute the amount of gross profit to be recognized each year, assuming the cost-recovery method is used.