The total cost of job 259 is $4,200. (a) When profit is calculated as 25 per cent
Question:
The total cost of job 259 is $4,200.
(a) When profit is calculated as 25 per cent of sales, the correct selling price for the job is $
(b) When profit is calculated as 25 per cent of cost, the correct selling price for the job is $