A company absorbs overheads on machine hours which were budgeted at 11250 with overheads of 258 750.
Question:
A company absorbs overheads on machine hours which were budgeted at 11250 with overheads of 258 750. Actual results were 10980 hours with overheads of 254 692. Overheads were: A B under-absorbed by 2152 over-absorbed by 4058 C under-absorbed by 4058 D over-absorbed by 2152