In a CPM/PERT analysis the focus is on________ and the events that link them together with the

Question:

In a CPM/PERT analysis the focus is on________ and the events that link them together with the finished project.

(a) costs, budgets

(b) activities, sequences

(c) timetables, budgets

(d) goals, costs