Master and flexible budgets An organization plans to make a product in batches of 25,000 units. Planned

Question:

Master and flexible budgets An organization plans to make a product in batches of 25,000 units. Planned production is 1,000,000 units, and actual production is 1,125,000 units. What are the planned (master budget) number of batches and the flexible budget number of batches?

(LO 1)