Glove Co. makes high quality, handmade gloves which it sells for an average of $180 per pair.

Question:

Glove Co. makes high quality, handmade gloves which it sells for an average of $180 per pair. The standard cost of labour for each pair is $42 and the standard labour time for each pair is three hours. In the last quarter, Glove Co. had budgeted production of 12,000 pairs, although actual production was 12,600 pairs in order to meet demand. 37,000 hours were used to complete the work and there was no idle time. The total labour cost for the quarter was $531,930.
At the beginning of the last quarter, the design of the gloves was changed slightly. The new design required workers to sew the company’s logo on to the back of every glove made and the estimated time to do this was 15 minutes for each pair. However, no-one told the accountant responsible for updating standard costs that the standard time per pair of gloves needed to be changed. Similarly, although all workers were given a 2 per cent pay rise at the beginning of the last quarter, the accountant was not told about this either. Consequently, the standard was not updated to reflect these changes.
When overtime is required, workers are paid 25 percent more than their usual hourly rate.


Required:

(a) Calculate the total labour rate and the total labour efficiency variances for the last quarter.

(b) Analyse the above total variances into component parts for planning and operational variances in as much detail as the information allows.

(c) Assess the performance of the production manager for the last quarter.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Management And Cost Accounting

ISBN: 9781473773615

11th Edition

Authors: Mike Tayles, Colin Drury

Question Posted: