Question:

Refer to Question 4.

Suppose that you expected your niece to work 1/2 hour for each lemonade sold. What is the labor efficiency variance, given that 7 lemonades were sold?

A. $0.50 unfavorable B. $0.625 unfavorable C. $1 unfavorable D. $1 favorable