Basic. Based on the data below, what is the amount of the overhead under-/over-absorbed? Budgeted overheads $493

Question:

Basic. Based on the data below, what is the amount of the overhead under-/over-absorbed?

Budgeted overheads $493 200 Budgeted machine hours 10960 Actual machine hours 10493 Actual overhead $514157

(a) $20957 under-absorbed

(b) $21015 over-absorbed

(c) $21015 under-absorbed

(d) $41.972 under-absorbed