Intermediate In a period, 5792 units were made with a standard labour allowance of 6.5 hours per
Question:
Intermediate In a period, 5792 units were made with a standard labour allowance of 6.5 hours per unit at £5 per hour. Actual wages were £6 per hour and there was an adverse efficiency variance of £36000.
How many labour hours were actually worked?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Question Posted: