7-32 Learning Curve and Cost Estimation The Smyth Company, a subcontractor for the aircraft and missile industry,
Question:
7-32 Learning Curve and Cost Estimation The Smyth Company, a subcontractor for the aircraft and missile industry, has been asked to bid on a prospective contract for 900 units of a precision missile part. Two months ago, the Smyth Company had produced 300 of these parts at the following total costs:
Direct materials $12,000 Direct labor (6,000 hours @ $4.00) 24,000 Tooling cost 3,000 Variable overhead” 3,000 Other overhead® 6,000 Total costs $48,000
* Tooling can be reused, even though all of its cost was assigned to the original order of 300 parts.
> Variable-overhead incurrence is directly affected by direct-labor hours.
° Other overhead is assigned at a flat rate of 25 percent of direct-labor cost for purposes of bidding on contracts.
The Smyth Company has used an 80 percent learning curve as a basis for forecasting what pertinent costs should be.
Prepare a prediction of the total expected costs for bidding on a contract of 900 units.