For the project described in Exercise 1, consider this situation. Your team has really performed well. The

Question:

For the project described in Exercise 1, consider this situation. Your team has really performed well. The six-month launch date is rapidly approaching, and you have figured out a way to meet the deadline. To meet the deadline, you will have to either fast-track or crash four activities of the testing phase (system testing, integration testing, security testing, and acceptance testing) before you can go into deployment, training, and documentation. What method would you choose? Why?