Look again at the activities outlined in Problem 1. Assume that during the first week of the
Question:
Look again at the activities outlined in Problem 1.
Assume that during the first week of the project your team discovers that the activity duration estimates were all wrong. Rather than 3 weeks, Activity 2 will take only two weeks to complete, whereas both Activities 4 and 7 will take three times longer than originally estimated. Further, all other activities will take twice as much time to complete. In addition, your team has noticed that additional training is needed. This new activity, number 11, will take one week to complete, and depends on the completion of Activities 10 and 9.
Create a new network diagram representing the new earliest expected completion times.