The planned value for a project is US$17,800, the earned value is US$19,450, and the actual cost

Question:

The planned value for a project is US$17,800, the earned value is US$19,450, and the actual cost is US$21,870. Based on this information, calculate the cost performance index and the schedule performance index. What do these indices tell you about the status of the project in terms of cost and schedule?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Information Systems Project Management A Process Approach

ISBN: 9781943153541

2nd Edition

Authors: Christoph Schneider, Mark A Fuller, Joseph S Valacich, Joey George

Question Posted: