Direct Labor and Indirect Labor Journal Entries (Actual Cost System). For the week ending July 26, 20x0,
Question:
Direct Labor and Indirect Labor Journal Entries (Actual Cost System). For the week ending July 26, 20x0, Buildrite Construction Company incurred direct labor costs of $20.000 and indirect labor costs of $2,500. Prepare the journal entries to record these transactions on an actual cost system.