Picard Landscaping plants grass seed as the basic landscaping for business campuses. During a recent month, the

Question:

Picard Landscaping plants grass seed as the basic landscaping for business campuses.

During a recent month, the company worked on three projects (Remington, Chang, and Wyco). The company is interested in controlling the materials costs, namely the grass seed, for these plantings projects.

In order to provide management with useful cost control information, the company uses standard costs and prepares monthly variance reports. Analysis reveals that the purchasing agent mistakenly purchased poor-quality seed for the Remington project. The Chang project, however, received higher-than-standard-quality seed that was on sale. The Wyco project received standard-quality seed. However, the price had increased and a new employee was used to spread the seed.

Shown below are quantity and cost data for each project.

Actual Standard Total Project Quantity Costs Quantity Costs Variance Remington 500 lbs. $1,200 460 lbs. $1,150 $ 50 U Chang 400 920 410 1,025 105 F Wyco 550 1,430 480 1,200 230 U Total variance $175 U Instructions

(a) Prepare a variance report for the purchasing department with the following columns:
(1) Project, (2) Actual Pounds Purchased, (3) Actual Price, (4) Standard Price, (5)
Price Variance, and (6) Explanation.

(b) Prepare a variance report for the production department with the following columns:
(1) Project, (2) Actual Pounds, (3) Standard Pounds, (4) Standard Price, (5) Quantity Variance, and (6) Explanation.AppendixLO1

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: