Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing Costs

Question:

Tierney Company begins operations on April 1. Information from job cost sheets shows the following.

Manufacturing Costs Assigned Job Month Number April May June Completed 10 $5,200 $4,400 May 11 4,100 3,900 $2,000 June 12 1,200 April 13 4,700 4,500 June 14 5,900 3,600 Not complete Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion.

Instructions

(a) What is the balance in Work in Process Inventory at the end of each month?

(b) What is the balance in Finished Goods Inventory at the end of each month?

(c) What is the gross profi t for May, June, and July?

AppendixLO1

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: