Which is a true statement regarding using a higher discount rate to calculate the net present value
Question:
Which is a true statement regarding using a higher discount rate to calculate the net present value of a project?
(a) It will make it less likely that the project will be accepted.
(b) It will make it more likely that the project will be accepted.
(c) It is appropriate to use a higher rate if the project is perceived as being less risky than other projects being considered.
(d) It is appropriate to use a higher rate if the project will have a short useful life relative to other projects being considered.