Assume a job with one stair climber requires 5 direct labor (DL) hours to produce: 3 DL

Question:

Assume a job with one stair climber requires 5 direct labor (DL) hours to produce: 3 DL hours in the Machining Department and 2 DL hours in the Assembly Department. Use the plantwide overhead rate and departmental allocation rates calculated in the chapter example to answer the following: 

1. How much MOH would be allocated to the job using the plantwide overhead rate? 

2. How much MOH would be allocated to the job using the departmental overhead rates? 

3. Does the plantwide overhead rate overcost or undercost the job? By how much?