Furry Friends Inc. manufactures toy stuffed animals. The direct labor time required to cut, sew, and stuff a toy is 10 minutes per unit. The company makes two types of stuffed toys—a lion and a bear. The lion is assembled in lot sizes of 60 units per batch, while the bear is assembled in lot sizes of 6 units per batch. Since each product has direct labor time of 10 minutes per unit, management has determined that the lead time for each product is 10 minutes. Is management correct? What are the lead times for each product?