Use the following abbreviations: Prime costs = PC Conversion costs = CC Direct materials

Question:

Use the following abbreviations:

• Prime costs = PC
• Conversion costs = CC
• Direct materials costs = DM
• Direct labour costs = DL
• Manufacturing overhead costs = MOH

Develop an equation that connects PC and CC.