12 A certification program consists of a series of activities that must be accomplished in a certain

Question:

12 A certification program consists of a series of activities that must be accomplished in a certain order.

The activities, their immediate predecessors, and estimated durations appear in the following table.

ACTIVITY IMMEDIATE PREDECESSORS TIME

(days)

A — 2 B — 5 C — 1 D B 10 E A, D 3 F C 6 G E, F 8

(a) Develop a project network for the certification program.

(b) Determine the EST, EFT, LST, LFT, and slack for each activity. Also determine the total program completion time and the critical path(s).

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: