12 A certification program consists of a series of activities that must be accomplished in a certain
Question:
12 A certification program consists of a series of activities that must be accomplished in a certain order.
The activities, their immediate predecessors, and estimated durations appear in the following table.
ACTIVITY IMMEDIATE PREDECESSORS TIME
(days)
A — 2 B — 5 C — 1 D B 10 E A, D 3 F C 6 G E, F 8
(a) Develop a project network for the certification program.
(b) Determine the EST, EFT, LST, LFT, and slack for each activity. Also determine the total program completion time and the critical path(s).