49 Elena Wilhelm is responsible for developing a comprehensive sales training program for her organization. The following

Question:

49 Elena Wilhelm is responsible for developing a comprehensive sales training program for her organization.

The following table describes the relationships between the activities that need to be completed:

ACTIVITY DAYS IMMEDIATE MINIMUM MAXIMUM PREDECESSORS A 7 13 —

B 5 11 —

C 3 8 A, B D 5 9 C E 2 9 C F 3 5 E G 5 12 F H 9 12 D I 6 8 F, H J 7 10 G, I Assume that the actual duration of each activity follows a discrete uniform distribution between the minimum and maximum times shown for that activity. Use simulation to determine the probability that the project will be finished in less than 49 days. Round off each activity time to the nearest whole number.