Complete the designated calculations for the following subsets of activities. Each subset is independent of the other subsets in the problem.
(a) Activity H has an EFT of 12 days. Activity I has an EFT of 15 days. Compute the EST for each activity in this table:
(b) Activity V has an EST of 13 days. Compute the EFT for each activity in this table:
(c) Activity T has an LFT of 50 days. Compute the LFT for each activity in this table:
(d) Activity E has an LST of 16 days. Compute the LST for each activity in this table: