Consider the data for a simple project as given in the following table. (a) What is the

Question:

Consider the data for a simple project as given in the following table.


(a) What is the critical path? What is the expected completion time of the project?

(b) What is the probability of all activities on the critical path being completed within 29 days?

(c) What is the probability of all activities on the other (noncritical) path being completed within 29 days?

(d) Is it safe to say that the probability of the project being completed with 29 days is equal to your answer from part (b)?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Managerial Decision Modeling Business Analytics With Spreadsheet

ISBN: 9781501515101

4th Edition

Authors: Nagraj Balakrishnan, Barry Render, Ralph Stair, Charles Munson

Question Posted: