Consider the data for a simple project as given in the following table. (a) What is the
Question:
Consider the data for a simple project as given in the following table.
(a) What is the critical path? What is the expected completion time of the project?
(b) What is the probability of all activities on the critical path being completed within 29 days?
(c) What is the probability of all activities on the other (noncritical) path being completed within 29 days?
(d) Is it safe to say that the probability of the project being completed with 29 days is equal to your answer from part (b)?