80. During a project review meeting, you discover that the planned value is $400,000, the actual costs

Question:

80. During a project review meeting, you discover that the planned value is $400,000, the actual costs are $325,000, and the earned value is $300,000. You can therefore conclude that:

A. The project is behind schedule and overrunning costs.

B. The project is ahead of schedule, but costs are higher than budgeted.

C. The project is behind schedule with costs under control.

D. The project is on schedule, but costs are higher than budgeted.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Question Posted: