Activity B on your network diagram has a most likely estimate of 8 days, a pessimistic estimate

Question:

Activity B on your network diagram has a most likely estimate of 8 days, a pessimistic estimate of 11 days, and an optimistic estimate of 6 days. What is the three - point estimate for this task rounded to the nearest whole number?

A. 11 days B. 25 days C. 8 days D. 6 days