Activity B on your network diagram has a most likely estimate of 8 days, a pessimistic estimate
Question:
Activity B on your network diagram has a most likely estimate of 8 days, a pessimistic estimate of 11 days, and an optimistic estimate of 6 days. What is the three - point estimate for this task rounded to the nearest whole number?
A. 11 days B. 25 days C. 8 days D. 6 days
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
CompTIA Project+ Study Guide: Exam PK0-003
ISBN: 9780470585924
1st Edition
Authors: Kim Heldman, William Heldman
Question Posted: