Every status meeting should have time allotted for Risk Monitoring and Control. Which of the following sentences
Question:
Every status meeting should have time allotted for Risk Monitoring and Control. Which of the following sentences is not true?
A. Risk identification and monitoring should occur throughout the life of the project.
B. Risk audits should occur throughout the life of the project and are specifically interested in measuring the team’s performance in the Risk Identification and Risk Monitoring and Control processes.
C. Risks should be monitored for their status and to determine whether the impacts to the objectives have changed.
D. Technical performance measurement variances may indicate that a risk is looming and should be reviewed at status meetings.