Randy is a key technical resource for your project. You ve worked with Randy on past
Question:
Randy is a key technical resource for your project. You ’ ve worked with Randy on past projects and have identified him in the project charter as one of the team members who will work on the project. The charter has been published, and there is great excitement about this project. You ’ ve scheduled a meeting to talk to Randy ’ s functional manager next week.
Which of the following conditions does this describe?
A. Risk B. Assumption C. Deliverable D. Constraint