Refer to the first network in the above problem. (a) What is P(Te 23)? (b) What is

Question:

Refer to the first network in the above problem.

(a) What is P(Te 23)?

(b) What is P(Te 32)?

(c) For what value of Ts is the probability 95 percent that the project will be completed?