The network and associated requirements for systems analysts and programmers for the GUMBY project are as follows:
Question:
The network and associated requirements for systems analysts and programmers for the GUMBY project are as follows:
(a) Draw the network. Compute ESs, LSs, and total slack times.
(b) Then show the separate resource loadings for systems analysts and programmers, assuming ESs.
(c) Suppose the maximum weekly availability is eight systems analysts and five programmers. Can activities be scheduled to satisfy these constraints without delaying the project?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project Management For Business Engineering And Technology Principles And Practice
ISBN: 9780750683999
3rd Edition
Authors: John M Nicholas, Herman Steyn
Question Posted: