The table below lists activities for constructing a bridge over an operational railway line: (a) Construct a
Question:
The table below lists activities for constructing a bridge over an operational railway line:
(a) Construct a network diagram for the project
(b) Do forward and backward pass calculations to indicate early and late start and finish times
(c) Indicate the critical path
(d) Indicate the total and free slack of each activity