What is the ECV of a project involving the launch of a new product with an estimated
Question:
What is the ECV of a project involving the launch of a new product with an estimated development cost of $15 M, launch cost of $0.8 M, and an NPV for the future stream of earnings of $45 M if the probabilities for success are 70 percent in development and 50 percent in the market?