Which of the following is not true for critical path activities? A. The early start is always
Question:
Which of the following is not true for critical path activities?
A. The early start is always less than the late start.
B. These activities are on the longest path on the network diagram.
C. The float is zero.
D. The late finish is always the same as the early finish.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
CompTIA Project+ Study Guide: Exam PK0-003
ISBN: 9780470585924
1st Edition
Authors: Kim Heldman, William Heldman
Question Posted: