Which of the following is not true for critical path activities? A. The early start is always

Question:

Which of the following is not true for critical path activities?

A. The early start is always less than the late start.

B. These activities are on the longest path on the network diagram.

C. The float is zero.

D. The late finish is always the same as the early finish.