Which of the following is not true for the critical path? A. It has zero float. B.
Question:
Which of the following is not true for the critical path?
A. It has zero float.
B. It ’ s the shortest activity sequence in the network.
C. You can determine which tasks can start late without impacting the project end date.
D. It controls the project finish date.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
CompTIA Project+ Study Guide: Exam PK0-003
ISBN: 9780470585924
1st Edition
Authors: Kim Heldman, William Heldman
Question Posted: