Which of the following is true for float or slack time? A. It s calculated by

Question:

Which of the following is true for float or slack time?

A. It ’ s calculated by adding the durations of all activities and dividing by the number of activities.

B. It ’ s time that you add to the project schedule to provide a buffer or contingency.

C. It’s the amount of time an activity can be delayed without delaying the project completion.

D. It is only calculated on the longest path of the network diagram.