Which of the following is true for float or slack time? A. It s calculated by
Question:
Which of the following is true for float or slack time?
A. It ’ s calculated by adding the durations of all activities and dividing by the number of activities.
B. It ’ s time that you add to the project schedule to provide a buffer or contingency.
C. It’s the amount of time an activity can be delayed without delaying the project completion.
D. It is only calculated on the longest path of the network diagram.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
CompTIA Project+ Study Guide: Exam PK0-003
ISBN: 9780470585924
1st Edition
Authors: Kim Heldman, William Heldman
Question Posted: