Which risk response strategy would the project manager do first that reduces the probability or impact of
Question:
Which risk response strategy would the project manager do first that reduces the probability or impact of the event without altering the project’s objectives?
a. Avoidance
b. Acceptance
c. Mitigation
d. Transfer