You are a project manager for a telecommunications company assigned to a project to deploy a new

Question:

You are a project manager for a telecommunications company assigned to a project to deploy a new wireless network using a technology that does not have a proven track record.

You have requested vendor bids for portions of the development that will include researching various scenarios. What type of contract is most likely in this situation?

A. Fixed - price contract B. Time and materials contract C. Cost - reimbursable contract D. A procurement method other than a contract