You are developing a bottom - up estimate for the first phase of your project. Which of

Question:

You are developing a bottom - up estimate for the first phase of your project. Which of the following is the most important input to complete this task?

A. Historic data from a similar project B. Chart of accounts C. The WBS D. The scope statement

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: