You are the project manager for a top secret software project for an agency of the United
Question:
You are the project manager for a top secret software project for an agency of the United States government.
Your mission—should you choose to accept it—is to complete the project using internal resources. The reason is that finding contractors with top secret clearances takes quite a bit of time and waiting for clearances would jeopardize the implementation date. Your programmers are 80 percent of the way through the programming and testing work when your agency appoints a new executive director. Slowly but surely your programmers are taken off this project and reassigned to the executive director’s hot new project. Which of the following type of project ending is this?
A. Starvation B. Extinction C. Addition D. Integration
Step by Step Answer:
PMP: Project Management Professional Study Guide
ISBN: 9780782136012
3rd Edition
Authors: Kim Heldman